Healthcare Buildings
Cantonal Hospital St. Gallen, Relocation coordination, project ‘Get Together’ H07A
Client
St. Gallen Cantonal Hospital
Location
Area of the St. Gallen Cantonal Hospital
Project duration
April 2022 - June 2024
Total Costs
425,000 CHF
With the construction of the building 07A, a new building was added to the area of the Cantonal Hospital of St. Gallen. The handover of the areas to the operation was planned for September 2023. The move to the new building 07A was then planned in coordination with the project H07A and was carried out in three stages. The move included goods, medical technology and patients. The operating theatre and intensive care unit areas were particularly challenging and complex.
Drees & Sommer Switzerland supported the St. Gallen Cantonal Hospital in this area in the role of lead relocation coordinator.
Added value
- The added value lies in the successful project implementation, but especially in the lessons learned from the situations that had to be dealt with flexibly due to unforeseen circumstances.
Individual services
- Management and coordination of the removal service provider through all phases
- Implementation of quality controls (PQM)
- Support for the client's project management
- Removal coordination
- Rough schedule
- Routeing
- Creation of tender documents for removal service providers
- Control of planning and tendering
- Preparation of the scope of services for the removal
- Control of the tendering and awarding of contracts
- Detailing of the rough concept in coordination with the sub-project managers and users
Checking the planning - Detailed planning of the moving days
- Creating moving manuals
- Conducting debriefing on the move ‘Lessons learned’