Infrastructure Provision

New construction of Bözberg tunnel, SBB AG

Client

Swiss Federal Railways SBB AG

General planner

IG BB-N+ c/o Gähler und Partner AG

Project duration

2015 – 2022

In order to expand freight traffic and transport goods faster through Switzerland, Swiss Federal Railways has been commissioned by the federal government to build a 4-metre corridor (clearance height for transporting semi-trailers on trains) by 2020. The largest single project is the construction of the new Bözberg tunnel between Effingen and Schinznachdorf in the canton of Aargau. The dimensions of the current tunnel are not suitable for 4-metre trains.
 
Work on the new Bözberg tunnel began in 2015 in several stages and was completed by 2020. The old tunnel has since been decommissioned and converted into a service and rescue tunnel.
 
The project cost CHF 350 million.

Added value

  • Creation of a 4-metre tunnel through the Bözberg as part of a new freight corridor

Individual services

  • Construction phase planning