Educational & Research Institutions

A new school campus "EIDE" in Differdange

Client

Administration Communale de Differdange

Project location

Differdange, Luxemburg

Architects

Bruck + Weckerle Architekten

Project duration

January 2016 - September 2022

Costs

34 Mio. €

Gross floor area

9.000 m²

Gross building volume

39.000 m³

Usable space (DIN 277)

4.800 m

The municipality of Differdange commissioned Drees & Sommer at the beginning of 2016 with project control services for the new construction of the transition structure of the International School. The primary objective was to find a solution to carry out the construction work within a tight schedule. The transitional structure was realized on the site of Differdange's former waste management yard. To ensure that the school could start its regular operations for 450 students from Sept. 2019, the work was awarded to a general contractor through a functional tender. The realisation was carried out within 11 months. The transitional structure is one of 3 three individual buildings on this site. 

Added value

  • Professional implementation of the client's interests

Individual services

  • Project management