Energy Supply (electricity, gas, district heating)
EnBW Fuelswitch
EnBW Energie Baden-Württemberg AG
Heilbronn and Altbach/Deizisau
March 2024—December 2026
electrical output 675 MW with 1,140 MW thermal output and 170 MW output for district heating network
electrical output 665 MW with 1,140 MW thermal output and 180 MW thermal output for the district heating network
As a result of the decision to phase out coal, EnBW is planning to shut down its coal-fired power plants at the Heilbronn and Altbach/Deizisau sites as part of the Fuel Switch project. It will then replace them with a gas-fired combined cycle power plant for the generation of electricity and heat in combined heat and power (CHP).
Drees & Sommer is taking over the complete site management (excluding HSE management) at the Heilbronn and Altbach/Deizisau sites for the Fuel Switch project. This includes overall construction management, specialized construction management of all trades, commissioning management, technical involvement in commercial/contractual order processing, interface/site coordination, technical quality assurance during assembly, scheduling, construction supervision, and other supporting functions.
Added value
- Coordination on the construction site is effective and technical construction management ensures smooth coordination
Services
- Site management (Project management, overall construction management, specialized construction management, commissioning coordination, technical quality assurance during assembly, scheduling, construction supervision)