Project duration
April 2009 – March 2017
Architect
agn Niederberghaus & Partner GmbH, Halle/Saale
GFA
20,103 m²
Budget
€ 85.040.000
Munich’s continued expansion poses new challenges for the Bavarian capital’s fire service. Fire Station 4 – the first of ten fire stations in Munich to be relocated to new buildings –was completed in three years with Drees & Sommer support throughout the project.
Additional value
- The constant presence of expert teams guarantees successful completion of a complex project.
Individual services
- Project Control
- ProjectCommunicationSystem (PCS)
- e.BIX Online Room Book
- Technical & Economic Controlling (TEC)